Προμήθειες: IGI-Poseidon SA

7 αρχειοθετημένες προμήθειες

Πρόσφατες προμήθειες από IGI-Poseidon SA

2019-05-17   Environmental and Social Impact Assessment (ESIA) and Permitting Support Services for the Offshore Sections of the... (IGI-Poseidon SA)
Environmental and Social Impact Assessment (ESIA) for environmental permitting and implementation of activities to obtain Authorization and Permits for the installation of the following EastMed offshore sections: — from SE Peloponnese till Atherinolakkos area (SE Crete), — from Atherinolakkos till Vassiliko (Cyprus), — from Vassiliko till the Eastern Mediterranean gas source. Indicative pipeline diameter: 26”-28” (subject to assessment and confirmation). Onshore Compressor Station (CS) (Vassiliko) and … Δείτε την προμήθεια »
Αναφερόμενοι προμηθευτές: ERM Italia S.p.A.
2018-07-09   Supply of Turbo-Compressor Packages for High Pressure Natural Gas Pipeline (IGI-Poseidon SA)
Design, manufacture, supply, transportation, installation, testing and commissioning of turbo-compressor packages for the high pressure natural gas pipeline. Indicatively each package will be complete with: — gas turbine and centrifugal natural gas compressor, — combustion air intake system, — fuel gas system skid, — gas turbine dry low emission system, — gas turbine discharge stack with silencer, — gas turbine enclosure complete with fire detection and firefighting systems for indoor installation, — … Δείτε την προμήθεια »
2018-07-04   Supply of Line Pipe and Auxiliary Items (IGI-Poseidon SA)
The contract concerns the supply of carbon steel line pipe. The Pipeline route has the following characteristics in relation to line pipe supply: — Location: Greece, Italy and seabed between, — Onshore Section, 48” nominal outer diameter, approx. 760 km length, — Offshore Section Pipeline, 36” nominal outer diameter, approx. 216 km length, — Offshore Pipeline Design Code: EN 14161 (ISO 13623) plus DNV standards for guidance as required, — Onshore Pipeline Design Code: EN 1594 and EN ISO 3183 (for line … Δείτε την προμήθεια »
2018-07-04   Engineering, Procurement and Construction of the Onshore Sections of the Poseidon Pipeline (IGI-Poseidon SA)
The contracts concern the engineering, procurement and construction of the onshore sections. The pipeline has the following characteristics in relation to the whole Onshore Section: 48”nominal outer diameter with wall thicknesses in the range 18,4mm to 26,2 mm, approx. 760 km length from Greece-Turkey Border to Thesprotia; Onshore Pipeline Design Code: EN 1594, designed for high pressure transmission (100 barg design pressure) of sweet, dry natural gas. Δείτε την προμήθεια »
2018-06-28   Front End Engineering Design of Facilities (Compressor and Metering Stations) for the EastMed Pipeline Project (IGI-Poseidon SA)
The Contract concerns the provision of Front end engineering design services related to the facilities (Compressor and metering stations) of the East Mediterranean project (EastMed) The EastMed project has the following characteristics in relation to the Facilities FEED: — Compressor stations in Cyprus (approx..100 MW), Crete (approx. 120 MW) for flow of approximately 10 Bscm/yr (sweet natural gas) and intermediate compressor station(s) on mainland Greece in an expansion phase, Fiscal metering and … Δείτε την προμήθεια »
2018-06-28   Front End Engineering Design of Offshore Pipeline for the East Mediterranean Project (EastMed) (IGI-Poseidon SA)
The Contract concerns the provision of Front end engineering design services related to the offshore pipeline sections of the Eastern Mediterranean pipeline project (EastMed) which will allow to transport natural gas from South Eastern Mediterranean basin to Western Greece (Thesprotia Prefecture). The EastMed project has an initial nominal gas capacity transported to Western Greece of approx. 10 Bcm per year with possible upgrade up to 20 Bcm per year. The main technical characteristics in relation to … Δείτε την προμήθεια »
2018-06-01   Front End Engineering Design of Onshore Pipeline for the East Mediterranean Project (EastMed Pipeline) (IGI-Poseidon SA)
The contract concerns the provision of Front End Engineering Design services related to the onshore pipeline section of the East Mediterranean Project (EastMed). The EastMed Project has the following characteristics in relation to the onshore pipeline FEED: — Approx. 550 km high pressure natural gas pipeline between a landfall in the southern Peloponnese of Greece to Thesprotia on the NW coast of Greece, — Indicative pipeline diameter in the range 42”-48” (subject to assessment and confirmation), — the … Δείτε την προμήθεια »